Chairman CDA visits Margalla Avenue N5 to M1 Extension and Sangjani Interchange project, reviews development works
ISLAMABAD: 13 November, 2026 : Chairman Capital Development Authority (CDA) and Chief Commissioner Islamabad Sohail Ashraf, accompanied by relevant senior officers, visited the Margalla Avenue N5 to M1 Extension and Sangjani Interchange project and carried out a detailed review and inspection of various sections of the project.
While briefing Chairman CDA Sohail Ashraf, it was said that construction activities are continuing vigorously on a 24/7 basis every day at various sections of the project and overall 36 percent of the development works of this project have been completed so far.
During the briefing, Chairman CDA was informed that under this project, work on the extension of the main highway, approximately 2.7 kilometers in length, is continuing swiftly on all sections, while work is also being carried out on the service road connected to the main road.
During the briefing, it was said that the structural work of the underpass included in the Sangjani Interchange project has been completed, and the concrete walls and footing slabs of the underpass have also been completed, while the remaining work, including earthwork and filling work, will also be completed soon.
During the briefing, it was apprised thatthe pile work of the abutments on both sides of the N-5 Interchange Bridge has been completed, while steel fixing and framework work is continuing swiftly. Similarly, the work on four culverts included in this project has been completed, while work on one culvert is ongoing. He was further informed that work is also being carried out swiftly day and night on all the loops and ramps included in the project.
Chairman CDA Sohail Ashraf directed that all obstacles in the way of the project within the stipulated period be removed and said that special attention be paid to quality, speed and transparency in the construction work of the project.
Chairman CDA Sohail Ashraf said that the completion of the project will provide easy access to Islamabad for those traveling within and outside the City, especially citizens coming from Khyber Pakhtunkhwa. Similarly this project will prove to be a gateway for those coming from other cities. He further said that this proje
While briefing Chairman CDA Sohail Ashraf, it was said that construction activities are continuing vigorously on a 24/7 basis every day at various sections of the project and overall 36 percent of the development works of this project have been completed so far.
During the briefing, Chairman CDA was informed that under this project, work on the extension of the main highway, approximately 2.7 kilometers in length, is continuing swiftly on all sections, while work is also being carried out on the service road connected to the main road.
During the briefing, it was said that the structural work of the underpass included in the Sangjani Interchange project has been completed, and the concrete walls and footing slabs of the underpass have also been completed, while the remaining work, including earthwork and filling work, will also be completed soon.
During the briefing, it was apprised thatthe pile work of the abutments on both sides of the N-5 Interchange Bridge has been completed, while steel fixing and framework work is continuing swiftly. Similarly, the work on four culverts included in this project has been completed, while work on one culvert is ongoing. He was further informed that work is also being carried out swiftly day and night on all the loops and ramps included in the project.
Chairman CDA Sohail Ashraf directed that all obstacles in the way of the project within the stipulated period be removed and said that special attention be paid to quality, speed and transparency in the construction work of the project.
Chairman CDA Sohail Ashraf said that the completion of the project will provide easy access to Islamabad for those traveling within and outside the City, especially citizens coming from Khyber Pakhtunkhwa. Similarly this project will prove to be a gateway for those coming from other cities. He further said that this proje
More from the gallery
View all
20 Nov 2026
Chairman CDA Visits F-7 Markaz, Jinnah Super Market, Detailed Review of Uplift and Renovation Work

19 Nov 2026
Chairman CDA visits the under construction National Police Academy project in Sector H-11 and inspects construction work, 96 percent of construction work completed

18 Nov 2026
Chairman CDA along with Member Environment, visits Babur Park, for detailed review of ongoing development works

18 Nov 2026
Chairman CDA visits Margalla Avenue Extension N5 to M1 and Sangjani Interchange project, 41 percent of development work completed

17 Nov 2026
Work on the Pandorian Model Graveyard project spanning over 860 kanals of land in Islamabad is continuing at a fast pace, soon the citizens of Islamabad will have the facility of a new graveyard

14 Nov 2026